FERC / DOMINION - COVE POINT - Actual TIMELINE

ACTUAL TIMELINE

2009 - DRAFT RESOURCE DOCUMENTS
Dominion started filling draft resource documents to FERC

June 2012 - PRE FILING PROCESS
 FERC approved Dominion’s entering the pre-filing process 

July 2012  - OPEN HOUSE
FERC staff attended a Dominion sponsored open house

Sept 24, 2012 - NOTICE OF INTENT
FERC issued a Notice of Intent to prepare an environmental document,
 which opened a scoping period. 

Sept 24, 2012  SCOPING PERIOD OPENED
(2 weeks later:  how could this possibly be announced 30 days in advance?)

9 Oct 2012 - FIRST ENVIRONMENTAL SCOPING MEETING 
         “we are basically in an early review 
so that we can have early public involvement, 
early agency involvement to identify 
and concerns about the project.”

Nov. 2012 - Draft resource reports 
will be filed and available for viewing on FERC's eLibrary website.

April 2013 - Dominion's :FORMAL APPLICATION
FERC will evaluate the completeness of that application. 

Source: FERC - Dominion Cove Point LNP,LP
Docket No. PF12-16-000
Environmental Scoping Meeting

9 Oct 2012