Actual Timeline - APPALACHIAN GATEWAY PROJECT

FERC 101 - HOME PAGE

APPALACHIAN GATEWAY PROJECT
DOMINION / FERC  TIMELINE
Shorter - Smaller - Approved
DATE            

29 Sept 2009            Dominion files a request to utilize FERC pre-filing process




06 Oct 2009              Dominion approved request  in Docket No. PF09-15-000

October 2009           Dominion held seven open house public meetings
                                    FERC staff participated in three of the open houses
                                   
5 Nov 2009               Draft resource reports filed

4 Dec 2009               FERC issued "Notice of intent to Prepare an Environmental                                     Assessment & Resuest for Comments on Enviromental Issues"                                           (NOI)

8 Jan 2010                FERC issued a Notice of Public Scoping Meetings for AGP

13 Jan 2010              Draft resource reports file

20 Jan 2010              FERC public scoping meeting, West Newton, PA

21 Jan 2010              FERC public scoping meeting, Waynesburg, PA

27 Jan 2010              FERC public scoping meeting, Pine Grove, WV

28 Jan 2010              FERC public scoping meeting, Belle, WV

27 Jan 2010              FERC Scoping meeting, Pine Grove WV

1 June 2010             Dominion filed an application in Docket No. CP10-448                                     under section 7 of the Subpart F of the Commission's                                     regulations for a  filed Certificate of Public Convenience and                                                 Necessity of the Natural Gas Act (NGA) and the certificate                                                        procedures of Part 157

26 July 2010             FERC interagency meetings with PADEP, 
                                    US Army Corps of Engineers, (USACE)

7 Oct 2010                USACE

9 Dec 2010               FERC issued letters to affected landowners on proposed and two                                     alternate routes

10 Jan 2011              Comment deadline for FERC letter to landowners (4 weeks)
                              
31 Mar 2011              Environmental Assessment for Docket No. CP10-448


6 May 2011               EA Comments deadline [5 weeks]

Source: 
APPALACHIAN GATEWAY PROJECT 
FERC No. PF09-15-000
DOMINION / FERC Scoping Meeting
Pine Grove, WV 
Jan. 27, 2010