DOMINION / FERC TIMELINE
Shorter - Smaller - Approved
Shorter - Smaller - Approved
DATE
29 Sept 2009 Dominion files a request to utilize FERC pre-filing process
06 Oct 2009 Dominion approved request in Docket No. PF09-15-000
October 2009 Dominion held seven open house public meetings
FERC staff participated in three of the open houses
5 Nov 2009 Draft resource reports filed
4 Dec 2009 FERC issued "Notice of intent to Prepare an Environmental Assessment & Resuest for Comments on Enviromental Issues" (NOI)
8 Jan 2010 FERC issued a Notice of Public Scoping Meetings for AGP
13 Jan 2010 Draft resource reports file
20 Jan 2010 FERC public scoping meeting, West Newton, PA
21 Jan 2010 FERC public scoping meeting, Waynesburg, PA
27 Jan 2010 FERC public scoping meeting, Pine Grove, WV
28 Jan 2010 FERC public scoping meeting, Belle, WV
27 Jan 2010 FERC Scoping meeting, Pine Grove WV
1 June 2010 Dominion filed an application in Docket No. CP10-448 under section 7 of the Subpart F of the Commission's regulations for a filed Certificate of Public Convenience and Necessity of the Natural Gas Act (NGA) and the certificate procedures of Part 157
26 July 2010 FERC interagency meetings with PADEP,
US Army Corps of Engineers, (USACE)
7 Oct 2010 USACE
9 Dec 2010 FERC issued letters to affected landowners on proposed and two alternate routes
10 Jan 2011 Comment deadline for FERC letter to landowners (4 weeks)
31 Mar 2011 Environmental Assessment for Docket No. CP10-448
6 May 2011 EA Comments deadline [5 weeks]
Source:
APPALACHIAN GATEWAY PROJECT
FERC No. PF09-15-000
DOMINION / FERC Scoping Meeting
Pine Grove, WV
Jan. 27, 2010