Saturday, July 19, 2014

BLASTING PLAN


"Procedures and safety, use, storage, 
and transportation of explosives 
that Dominion's contractor would follow 
should blasting be necessary. 
                                                                 
m
Edited by Lauren Ragland
wv.wilderness.vs.prop.pipeline@gmail.com

Source: 1.8 Erosion and Sedimentation Control Plan (ESCP)
Environmental Assessment for APPALACHIAN GATEWAY PROJECT 
OEP/DG2E/Gas3, Dominion Transmission Inc.
CP10-448-000, PF09-15-000
Federal Energy Regulatory Commission
Office of Energy Projects
Washington, DC
March 2011