& LAYDOWN AREAS
"These work areas would be located adjacent
to the construction right-of-way."
EXTRA CREDIT *
Additional construction areas, or temporary extra workspaces,
would be required for construction at :
road crossings
railroad crossings
crossing of existing pipelines and utilities,
stringing truck turnaround areas
wetland crossings
horizontal directional drill(HDD) entrance and exit pits
open-cut waterbody crossings.
Used for:
spoil storage
staging, equipment movement
materials stockpiles/laydown areas
pull string assembly associated with HDD installation
These work areas would be located adjacent to the construction right-of-way.
This EA for AGP involved eight pipeline rights-of-way, with extra workspaces estimated totaling 200.1 acres, with individual extra workspaces ranging in size from 0.01 acre to 2.39 acres. [see: EXTRA CREDIT]
SOURCE: 1.7.1 Extra Workspaces and Laydown Areas
Environmental Assessment for APPALACHIAN GATEWAY PROJECT, OEP/DG2E/Gas3, Dominion Transmission Inc., CP10-448-000, PF09-15-000, Federal Energy Regulatory Commission, Office of Energy Projects, Washington, DC, March 2011